BUSI 414 Week 8 Exam | Liberty University | Assignment HelpFinal Exam• Question
1 A
project has the following Earned value data assessed:AC: $ 4,000,000 CV: $ -500,000SPI: 1.12BaC: $9,650,000What is the Earned value of the project? • Question
2 A
project underwent a major Scope change, which increased cost and work levels.
What does this mean for Earned value data? • Question
3 _______